Pre startup check list (ugw-water-cooled) – ClimaCool UGW Manual User Manual

Page 27

Advertising
background image

25

www.climacoolcorp.com

Project Name: _________________________________________________Date:_________________________

Address: ___________________________________________________________________________________

YES NO

1. Are modules connected properly per Codes and Installation Manual?

___

___

(Installation, Operation & Maintenance Manual is available at www.climacoolcorp.com)

2. Does the module(s) nameplate voltage agree with the site voltage being supplied?

___

___

3. Is there a minimum of 60 mesh strainer on condenser and evaporator inlet water?

___

___

(Fill water to chiller being sure to pass through a minimum of 60 mesh strainer.)

4. Is condenser water system filled and flushed? (See “Filling the Water System” in ClimaCool IO&M.)

___

___

5. Is chilled water system filled, flushed and all air purged from system?

___

___

(Air must be purged from system prior to startup. See “Filling the Water System” in ClimaCool IO&M.)

6. Are all pumps tested and operational?

___

___

7. Is required GPM (verified by pressure differential) supplied to the chilled water side?

___

___

(See project specifications or selection and performance sheets available from ClimaCool Sales Rep.)

8. Is required GPM/Pressure differential being supplied to the condenser?

___

___

(See project specifications or selection and performance sheets available from ClimaCool Sales Rep.)

9. Pressure differential flow sensors set to trip on the drop below required flows?

___

___

(Set to trip on low flow (below 25% loss of flow), not pump on/off.)

10. Have all chiller coupling connections been leak tested?

___

___

11. Is water presently circulating through chiller?

___

___

12. Verified that temperature sensors and voltage/phase monitor have been installed?

___

___

13. Is power and communication wiring complete to each module?

___

___

14. Verify that wiring and devices meet with approved electrical submittal drawings?

___

___

15. Is required load available to run multiple compressors at startup?

___

___

16. Is control functional to maintain condenser water temperature?

___

___

(Includes maintaining “minimum” inlet temperature; see “Operational Limitations” in ClimaCool IO&M.)

17. Is a water header bypass installed at the chiller? Check one: ____ ClimaCool provided? ____Field provided?

If you checked “No” to any question above, provide the line reference number and the date of scheduled completion below.

Please note all conditions must be complete prior to the startup date.

__________________________________________________

__________________________________________________________________________________________________________________

__________________________________________________________________________________________________________________

*This form must be completed and submitted to ClimaCool a minimum of three (3) weeks prior to final scheduling of any startup.

……….

NOTE: If any of the above items are not complete at time of startup, back charges will be assessed for additional costs.

.........

....

Contractor Name: _________________________________________

Address:

_________________________________________

____________________________________________

_________________________________________

(Authorized Signature)

Phone:

_________________________________________

Date: _____________________________________________

Pre Startup Check List (UGW-Water-Cooled)

E-mail

[email protected]

Fax 405-815-3052

DOC: Pre Startup UGW-Water Cooled 7.2013

10/4/2013

SD#0011

Page:

Project Name:

Contractor:

Address:

Address:

City/ST/Zip:

City/ST/Zip:

Start-up Date:

Phone:

Model #:

Model #:

Serial #:

Serial # 1:

Chiller #:

Serial # 2:

Evaporator:

/

P

Evaporator:

Yes

N/A

Condenser:

/

P

Condenser:

Yes

N/A

Evaporator and Condenser "flow devices" shut off chiller below 25% loss of flow:

Yes

► All Wiring Terminations in module panel, safeties and compressors tightened:

Yes

No

Compressor terminal torques: Line lug M10-175 in/lbs (14.6 ft/lbs), Ground lug M10-371 in/lbs (30.9 ft/lbs)

Yes

No

L1

L2

L3

L1/L2

L2/L3

L1/L3

Check Voltage Imbalance:

Amperage:

L1

L2

L3

A-B

A-C

B-C

Sight Glass Oil Level:

Average Voltage:

(A-B + A-C + B-C)/3

Suction Pressure:

Max Deviation from Average Voltage:

Suction Temperature:

Voltage Imbalance Less than 2%:

Compressor Superheat:
Discharge Pressure:
Liquid Line Temperature:
Liquid Subcooling:

Oil Level within sight glass range:

Evaporator Leaving Water Temp.:

Oil Temperature must be at least

Condenser Entering Water Temp.:

68°F before starting:

Condenser Leaving Water Temp.:
Evaporator Pressure Differential:

Compressor Isolation Valves

Condenser Pressure Differential:

are fully open (if equipped):

Verify Safety Setting Limits:

Low Temp:

Rep Signature:

Print Name:

E-Signature:

Startup & Warranty Registration Form (Water-Cooled) UGW

Ambient

Temp:

E-mail

[email protected]

.

Fax 405-815-3052

Module

Compressor

Bank No.:

Bank Water Pressures Entering/Leaving

Water Samples Taken (Mark "X")

Low Voltage (24V):

For initial MANDATORY water samples, bottles are provided.

Follow instructions on label and mail the same day water sample is taken.

► Rotation of Screw Compressor is correct

Voltage / Ground

Phase / Phase

Evaporator Entering Water Temp.:

High Pressure:

Low Pressure:

Compressor Circuit # 1

DO NOT start chiller if Voltage Imbalance is greater

than 2%. Contact utility company for assistance.

(Maximum Deviation/Average Voltage) X 100

(Authorized Signature)

Check Box

Doc: Startup - Warranty Reg. Form (Water-Cooled) 7.18.2013
SD# 0010

10/9/2013

Page:

Project Name:

Contractor:

Address:

Address:

City/ST/Zip:

City/ST/Zip:

Start-up Date:

Phone:

Model #:

Model #:

Serial #:

Serial # 1:

Chiller #:

Serial # 2:

Evaporator:

/

P

Evaporator:

Yes

N/A

Condenser:

/

P

Condenser:

Yes

N/A

Evaporator and Condenser "flow devices" shut off chiller below 25% loss of flow:

Yes

► All Wiring Terminations in module panel, safeties and compressors tightened:

Yes

No

Compressor terminal torques: Line lug M10-175 in/lbs (14.6 ft/lbs), Ground lug M10-371 in/lbs (30.9 ft/lbs)

Yes

No

L1

L2

L3

L1/L2

L2/L3

L1/L3

Check Voltage Imbalance:

Amperage:

L1

L2

L3

A-B

A-C

B-C

Sight Glass Oil Level:

Average Voltage:

(A-B + A-C + B-C)/3

Suction Pressure:

Max Deviation from Average Voltage:

Suction Temperature:

Voltage Imbalance Less than 2%:

Compressor Superheat:
Discharge Pressure:
Liquid Line Temperature:
Liquid Subcooling:

Oil Level within sight glass range:

Evaporator Leaving Water Temp.:

Oil Temperature must be at least

Condenser Entering Water Temp.:

68°F before starting:

Condenser Leaving Water Temp.:
Evaporator Pressure Differential:

Compressor Isolation Valves

Condenser Pressure Differential:

are fully open (if equipped):

Verify Safety Setting Limits:

Low Temp:

Rep Signature:

Print Name:

E-Signature:

Startup & Warranty Registration Form (Water-Cooled) UGW

Ambient

Temp:

E-mail

[email protected]

.

Fax 405-815-3052

Module

Compressor

Bank No.:

Bank Water Pressures Entering/Leaving

Water Samples Taken (Mark "X")

Low Voltage (24V):

For initial MANDATORY water samples, bottles are provided.

Follow instructions on label and mail the same day water sample is taken.

► Rotation of Screw Compressor is correct

Voltage / Ground

Phase / Phase

Evaporator Entering Water Temp.:

High Pressure:

Low Pressure:

Compressor Circuit # 1

DO NOT start chiller if Voltage Imbalance is greater

than 2%. Contact utility company for assistance.

(Maximum Deviation/Average Voltage) X 100

(Authorized Signature)

Check Box

Doc: Startup - Warranty Reg. Form (Water-Cooled) 7.18.2013
SD# 0010

10/9/2013