Refrigeration system re-processing and charging – ClimaCool UGW Manual User Manual

Page 50

Advertising
background image

www.climacoolcorp.com

48

Conforming to local and national codes is the responsibility

of the service technician or installing contractor . The service

technician should be familiar with the following codes:
• ASHRAE Standard Safety Code for Mechanical

Refrigeration, ANSI/ASHRAE 15-1978

• American National Standard Code for Pressure Piping,

ANSI B31 .5-1974

Factory Tested

ClimaCool modular chillers have been pressure-tested,

evacuated, fully charged and run tested at design water

flow rates prior to shipment. In the unlikely event that

a refrigerant leak is detected at startup, the following

guidelines should be consulted before reprocessing the

refrigeration systems .

Refrigerant System Reprocessing

Debris and moisture can enter copper tubing in a matter

of minutes . All tubing, coil connections or any refrigerant

containing portions should be temporarily capped or sealed

to keep contaminants to a minimum . Filter driers should

be opened just prior to brazing into the system to prevent

moisture infiltration whenever possible, and flood the

system with low pressure dry nitrogen while brazing to

prevent oxidation inside the copper piping .
After all of the repairs have been made to the refrigeration

system, a pressure test using refrigerant and nitrogen

should be performed . Pressurize the system with dry

nitrogen to 20 psi and check for any obvious leaks . If no

leaks are present, introduce a “trace” amount of refrigerant

to the system (raise system pressure to 30-40 psi). With a

dry nitrogen tank equipped with a regulator set to 150 psi,

continue to pressurize the system to 150 psi . Using a leak

detector, carefully check the system for any remaining leaks .

If the system is free of leaks, release the pressure .

Evacuating the System

The compressors should never run while the system is

in a vacuum. This could cause immediate failure to the

compressors . After the system has been leak tested and

sealed, any moisture that entered the system should be

dehydrated and removed . While the pressure is reduced

under a vacuum, the boiling point of moisture trapped

inside the lines is also reduced . A pressure of .0095 psia, or

500 microns absolute pressure or better must be reached

and sustained for several hours in order for the system to

be considered free from moisture . It is necessary to use a

micron meter equipped with an absolute pressure gauge (or

transducer) to take this reading . ClimaCool recommends the

double evacuation process to ensure the proper removal of

moisture and contaminants from the refrigeration system .

After the initial vacuum is reached and held on the system,

allow dry nitrogen back into the system until the pressure

reaches zero psig or slightly higher . Then, repeat the entire

evacuation process described above . The evacuation

process is considered complete ONLY after a successful

“blank-off” test is performed.
A “blank-off” test is defined as:

Pulling a vacuum level less than 500 microns on the

system and holding it for several hours .

Record the vacuum level in the system in microns,

then close off the vacuum pump from the system for

15 minutes, and continue to monitor the micron level

inside the refrigeration system .

If the vacuum level inside the system does NOT rise

more than 400 microns above the recorded vacuum

level at the start of the 15 minute period, then the

evacuation process is complete .

If the vacuum level rises more than 400 microns in 15

minutes, then continue to evacuate the system for 1-2 hours,

and repeat a “blank-off” test.

Recharging the System

After all repairs have been completed, the system has

been leak tested and proper vacuum pressures have been

reached and maintained, refrigerant may be recharged

into the system . With a known weight of refrigerant in

the cylinder, use the gauge manifold set to connect the

cylinder’s liquid charging port to the charging access port

near the refrigerant liquid line valve . Gradually meter the

appropriate weight of liquid refrigerant into the condenser

side of the system first, until no additional refrigerant can

be dispensed . Accurate refrigerant charge per circuit may

be found in the Physical Data information on page 5 . Then

continue the charging process by filling the evaporator side

of the system with refrigerant . Close the refrigerant cylinder

charging port, close all gauge manifold ports and start the

compressor . Be careful when continuing to charge the

balance of the refrigerant, constantly maintaining a positive

compressor suction pressure (>25 psig) at all times.

Refrigeration System Re-Processing and Charging

Electronic Expansion Valve

Factory installed electronically operated expansion valve for

precise control of liquid refrigerant flow.

Figure 17

Advertising