14

INSTALLATION

SYSTEM GUIDELINES

Prints Specific per Installation

Often times, installation prints are custom drawn

for each site. You should check those prints for

information that is specific to your installation.

Any deviations from those prints made during or

after installation should be recorded for further

reference.

Cable Assemblies

Most electrical interconnections between the Dy-

naFlow controller and other system components

are made through cable assemblies.

NOTE

Any unused conduit holes must be blanked off

to prevent solid objects from entering the inte-

rior of the enclosure.

Equipment Grounding

The control panel should be grounded

in accordance with national and local

electrical codes.

C A U T I O N

!

The protective ground conductor must be

terminated directly to the protective conduc-

tor ground terminal located inside the Control

Enclosure which is marked with symbol -

Equipment Locations

With the exception of the following restrictions,

the installation of the Transducers or Transducer

Panel, the Remote Operators Station and Regu-

lator/Flow meter assemblies are application and

site dependant. Specific instructions for location

and mounting of these assemblies are covered

on the site installation drawings.

1. The maximum recommended distance from

the Control Panel to each flow meter is 100-ft.

as determined by the maximum standard avail-

able length of the fiber-optic cable assemblies or

intrinsic electrical cable assemblies.

2. The maximum recommended length of air pi-

lot tubing between the electrical-to-pneumatic

(E/P) transducer and the material regulator is

largely determined by the application. In general,

the pilot lines should be kept as short as pos-

sible to achieve the best fluid flow response and

regulation. See "Pilot Signal Guidelines" chart in

this section.

3. The maximum distance between the optional

LBAL5001-XX Pneumatic Interface Panel to the

Control Console is 40-ft., as determined by the

interconnecting electrical cable assembly.

4. The maximum recommended 1/4-inch OD

hose length from the LBAL5003, Remote Opera-

tor Panel, and the LBAL5001, Pneumatic Inter-

face Panel, is 50-ft., however this can be longer

depending on the application. The maximum

distance between the A12182 interface panel and

the A12233 console is 100-ft.

5. The maximum recommended length for the

E/P transducer electrical control cable is 95 ft.

However, in some cases 175-ft. has been used.

Generally, if a GUN number (not atomizers) con-

trols a complete zone of 6 or more atomizers, do

not exceed 95-ft. of cable.

Consult Ransburg if longer distances than those

shown above are desired.