Procedures, Dynaflow, User manual - operation – Ransburg DynaFlow User Manual User Manual

Page 58: Clean, First-time system start-up

Advertising
background image

LN-9400-00.9

DynaFlow

TM

User Manual - Operation

54

Clean

Any CHANNEL or Gun can be placed into a CLEAN

mode by an external command or through the Host

controller. The Clean mode forces the material

regulator fully open until turned OFF. The GUN

Enable and CLEAN inputs must be active and all

system or GUN faults cleared. To properly exit

the CLEAN MODE, the GUN Clean input should

be removed followed by a GUN Halt signal, or

a command issued from the Operator Interface

Panel (host controller). Each CHANNEL must be

set as a "clean" CHANNEL in the Clean CHANNEL

parameter located in the Gun Configuration table.

Make sure the proper channels are

configured to "clean" on the Gun Param-

eters screen.

NOTE

Full Error Detection

The DynaFlow controller will detect certain error

conditions and indicate the cause of the error

with a code. The code indicates the faulted Gun

and CHANNEL, as well as giving you a text error

message. All errors are categorized by CHANNEL,

Gun or System depending on the type of error.

The error codes and conditions are listed in the

appendix and include:

Tolerance errors in fluid flow rates for each

material

Tolerance errors in fluid flow ratios for each

material

Reverse fluid flow

Low material flow

High material flow

Pot-life timers expired

Memory errors

Backup disk errors

Configuration errors

System errors

PROCEDURES

First-Time System Start-Up

This section is intended for skilled trades person-

nel. Always be aware of safety guidelines while

operating equipment.

Before power is supplied to the DynaFlow Fluid

Flow Control, take time to familiarize yourself

with the controls. Unexpected actions can occur

during initial power-up sequences and you should

know which controls shut down the controller. The

following information serves as a guide for initial

system testing and start-up. Operational problems

will be avoided if time is taken to follow the steps

outlined below. Read through the entire sequence

first before performing any actions.

Verify that the Interface and Channel Mod-

ule dip switch settings are correct. Refer-

ence the HARDWARE SETTINGS section.

Visually inspect the entire system. Review

the "Installation" section of this manual and

any related manuals such as the flow meter

and material regulator. Verify that all air and

fluid lines are routed properly and fittings

are secure.

Make sure that the required fluid filtration is

installed. Fluid lines should be flushed out

manually before installation of the flow

meters to ensure that any large particles or

contamination located from the fluid filter to

the flow meter connection are removed.

Make sure that the required air filtration for

the E/P transducer(s) is installed.

If rotary applicators are used, remove the

front shroud and bell cup to expose the

paint feed tube. If GUNs are being used,

point the applicator(s) downward if pos-

sible. This will prevent the possibility of

material from contaminating the applicator

and provide additional safety for any per-

sonnel working near the system.

Turn ON the main power disconnect to the

fluid flow control panel.

Turn ON the power switch located on the

flow control panel.