9171300990 Rev V

BE1-87T Test Procedures

5-11

Step 3. Set the input under test to the 3.9 tap position as shown in Table 5-2. Set the RESTRAINED

PICKUP LEVEL switch to position A (15%). Apply current to the input under test, increasing

the current until the

REST. TRIP LED lights. At this point, the input current should be 1.36 A

±

6% ±100 mA.

Step 4. Repeat Step 3 for the additional tap positions shown in Table 5-2. This verifies the accuracy of

all the binary combinations of the rotary switches.

Step 5. Test the other inputs by reconnecting to the next pair of terminals for your relay and repeating

Steps 3 and 4. (The successful completion of these tests will verify the electrical integrity of all

the tap switches.)

Table 5-2. Input Verification*: 5 A, 50 or 60 Hz

Tap† Position

Input Current Range at Pickup

3.9

1.18 - 1.55 A

4.3

1.31 - 1.70 A

6.4

2.01 - 2.47 A

7.8

2.47 - 2.99 A

*

Pickup occurs at 0.35 x Tap. See Figure 1-2.

† The setting of the upper and lower

INPUT switches of the input being tested.

(Reference Location of Controls and Indicators.)

Unrestrained Pickup Verification

Step 1. Set the INPUT 1 (tap) switches to the 2.0 A position. Connect the relay as appropriate (refer to

Figures 5-1 through 5-4) using terminals 11 & 13 (Input 1 for both single-phase and three-

phase units).

Step 2. Set the UNRESTRAINED PICKUP LEVEL switch to position A (6 x TAP). Increase the input

current until the

UNREST. TRIP LED lights (disregard the REST. TRIP LED). This should occur

at 12.0 A

±

3% as indicated in Table 5-3.

Step 3. Repeat Step 2 using the other UNRESTRAINED PICKUP LEVEL switch positions given in

Table 5-3.

Step 4. For Three-Phase Units Only: Repeat Steps 1 through 3 for phase B of input 1 (terminals 12 &

13) and Phase C of input 1 (terminals 14 & 13).

Table 5-3. Unrestrained Pickup Verification: 5 A, 50 or 60 Hz

Unrestrained

Pickup Level

Input 1 Tap

Position

Input Current at

Pickup ±3%

A (6 x TAP)

2.0

12.0 A

J (14 x TAP)

2.0

28.0 A

S (21 x TAP)

2.0

42.0 A

Second-Harmonic Restraint Verification

Step 1. Set the INPUT 1 (tap) switches to the 2.0 A position. Connect the relay as appropriate (refer to

Figures 5-1 through 5-4; except set both current sources to 0° for second-harmonic restraint

verification) using terminals 11 & 13 (Input 1 for both single-phase and three-phase units).