Pumping down (re-installation) – Panasonic CS-A9CKPG User Manual

Page 57

Advertising
background image

1. Confirm that both the 2-way and 3-way valves are set to

the opened position.

Removethevalvestem caps and confirm that thevalve
stems are in the opened position.

Be sure to use a hexagonal wrench to operate the valve
stems.

2. Operate the unit for 10 to 15 minutes.

3. Stop operation and wait for 3 minutes, then connect the

charge set to the service port of the 3-way valve.

Connect thechargehosewith thepush pin to theGas
service port.

4. Air purging of the charge hose.

Open thelow-pressurevalveon thechargeset slightly
to purgeair from thechargehose.

5. Set the 2-way valve to the close position.

6. Operate the air conditioner at the cooling cycle and

stop it when the gauge indicates 1 kg/cm

2

G (0.1 MPa).

7. Immediately set the 3-way valve to the closed position.

Do this quickly so that thegaugeends up indicating 3 to
5 kg/cm

2

G (0.3 to 0.5 MPa).

8. Disconnect the charge set, and mount the 2-way and 3-

way valve’s stem nuts and the service port caps.

Use a torque wrench to tighten the service port cap to a
torqueof 1.8 kg.m (18 N.m).

Be sure to check for gas leakage.

12.1.2. Pumping down (Re-installation)

Procedure:

57

CS-A9CKPG CU-A9CKP6G / CS-A12CKPG CU-A12CKP6G