Patient leakage current ii – GW Instek GLC-9000 User Manual User Manual
Page 55

OPERATION
55
Patient Leakage Current II
Network
For medical network circuits only (MD-F), type B
only.
Connection
As illustrated, ensure that the power source and
test leads are properly connected.
Type B Medical
Network
1. Connect the test leads to the T2 & T3 terminals
and position the T2 test lead to the applied part
of the EUT.
2. Position the T3 test lead on an ungrounded
section of the signal I/O on the EUT.
The T3 terminal is high voltage. Avoid contact with the
terminal. The T3 terminal should not be connected
with an earth conductor.
Measurement
Setup
Confirm all settings including MD, leakage current
mode, measurement time, upper and lower limits,
and other parameters.
Panel Operation
3. Turn on the circuit breaker.
Connect the EUT to the
power socket.
GLC-9000