7 .3 Stream configuration

For each stream that is involved with switching, the following configuration must be set:

Figure 126 Stream configuration run switching

The configuration consists of 3 differen parts which will be describe in the following paragraphs:

General

Determines when to switch the stream

Valve control

Determines which valves must be controlled to switch

Flow control

Determines how to control the flow when through the stream

7 .3 .1 General

When run swiching needs to switch up (a new stream is added) it has to know which of the

streams to take. Each stream can be given a priority, from 1 (or always used) to 5 (last stream to

be added.

Also the flow switch point has to be given; add a new stream when above the maximum capacity

of the stream and close a stream when below a minimum capacity:

Figure 127 Stream run switching switch conditions

Run priority

Priority of this stream (1-5)

Max. capacity

Maximum capacity in % of the stream before opening a new stream

Min. capacity

Minimum capacity in % of the stream before closing a stream

Please ensure that for streams 2..5 the minimum capacity is chosen such that it

will be closed in time to arrive at a proper flow of the stream before, e.g. 45 %