SUMMIT 8800

METERING PRINCIPLES

03

A04

Begin prove valve

control

All configured valve are set to proper position. If configured the

following valves are set in the following sequence.
1. Set run flow control;

2. Open required run outlet;

3. Open prover outlet;

4. Set prover flow control;

5. Close all run prover inlet;

6. Open required run prover inlet;

7. Close run outlet;

8. Set 4-way valve to reverse, only for ball provers;

9. Start flow control.

Valve status tags can be found in the following location.

A05

Valves correctly

positioned?

All configured valves are check if they are in the proper position with

valve position tag.

1. Idle

2. Opening prover outlet valve

3. Opening prover flow control valve

4. Positioning fourway valve

5. Opening run prover inlet valve

6. Closing run prover inlet valve

7. Opening run flow control valve

8. Opening run outlet valve

9. Closing run outlet valve

10. Start regulating

11. Checking run outlet valves

12. Returning piston

13. Opening master run outlet

14. Closing master run outlet

A06

Flow stabilisation

Volume, temperature, and pressure are checked for deviations.
• Minimum stability duration, this is the waiting time before stability

check;

• Maximum stability duration, after this time the conditions must be

stable;

• Stability limit, the maximum limit for the deviation.

A07

Stabilisation completed

successfully?

Check is made if previous steps were successful.
Important: If successful the conditions are recorded and monitored

throughout the proving.

For reference the standard deviation tag for flow, temperature and

pressure can be found under the following location.

There are a set of deviation alarm tags that are set is the standard

deviation is greater than the limit set.

Active>prover>alarms>live>prover pressure-temperature-flow

A08

Proving sequence

In this step sub routine proving sequence is initiated. The result of the

sequence can be successful or failed

A09

Multi-point prove?

A check is made on how the prover is configured, single point or multi-

point.
If the prover is configured as multi-point proving, then the routine will

go back to step A06 ‘flow stabilisation’ and set the configured flow rate

for each proving point.

If the prover is configured as single point proving, then the routine will

continue to the next step.