Installing in pue hy housing – RADWAG HTY 60/H5/K Multifunctional Scales User Manual

Page 219

Advertising
background image

219

platforms connected

to indicators in metal

housing via a cable

only

platforms electrically

connected to indicators’

metal housings e.g.

pillars, racks

Load cells without internal

shield connection to the

tensometer body

POINT B

E

Load cells with internal

shield connection to the

tensometer body

POINT B

POINT B


Point B

– screwed terminal electrically connected to the metal housing

of the indicator (possible using of soldering eye).
E

– soldering pad on a DP2 PCB.


The way of checking connection between the shield and the tensometer
body

Use an ohmmeter for this purpose.

37.5.4. Installing in PUE HY housing

DP2

modules are intended to mount inside PUE HY housings. It is mounted

to the main board to the 10-pin J11 connector. For DP2 module an additional

gland is installed on the back wall of the housing.

Installing procedure:

1. Unplug the scale from mains;

2. Unscrew and take off the back wall of the housing;