Control bypass (test mode) – ETC Unison DRd Dimming Rack Enclosure User Manual

Page 58

Advertising
background image

54

DRd Enclosure Installation Manual

Step 6:

Power up the enclosure. Before installing or removing dimmer or control

modules for service, de-energize main feed to DRd and follow appropriate

Lockout/ Tagout procedures as described in NFPA Standard 70E. It is important

to note that electrical equipment such as dimmer enclosures can present an arc

flash safety hazard if improperly serviced. This is due to available large short

circuit currents on the feeders of the equipment. Any work on energized

equipment must comply with OSHA Electrical Safe Working Practices.

Step 7:

Switch all module circuit breakers to the “On” position.

Step 8:

Reference the related Architectural Control Processor Configuration Manual for

DRd configuration setup and operation.

Control Bypass (Test Mode)

Test load circuits connected to the DRd enclosure by switching the “Control Bypass” switch

to the “Test” position. The Control Bypass switch allows testing of lighting loads and

provides temporary lighting before complete system commissioning. Return the switch to

its “Normal” setting after the test is complete.

W A R N I N G :

Never power up or operate the DRd enclosure without all modules installed.

Failure to comply exposes you to dangerously high voltages that may result

in death by electrical shock.

C A U T I O N :

Turning the Control Bypass switch to the “Test” position with all module circuit

breakers “On” will bring all lighting loads to full. To select only certain lighting loads

for test, switch “Off” undesired module circuit breakers in the DRd enclosure.

Control Bypass switch

Advertising