Commissioning

During commissioning, plant-specific data such as motor parameters, operating

parameters, responses, and parameters for fieldbus communication are defined for the

controller. Lenze devices use codes for this purpose.
The codes of the controller and for communication are saved to the memory module in a

non-volatile data set.
In addition, there are codes for diagnosing and monitoring the stations.



Parameter reference

( 81)

6.1

Before initial switch-on

Stop!

Before switching on the controller for the first time, check ...
• the entire wiring for completeness, short circuit and earth fault.
• whether the bus system is terminated through a bus terminating resistor at

the first and last physical bus station.