5. Checklist for the assembly of T-Series arrays

5.1.

System and safety checks

5.1.1. Flown arrays

Before hoisting the array to its operating position recheck the actual
status of the assembly as follows:

- Check the attachment of the Load adapter(s) to the Flying frame and

ensure all Locking pins are properly locked.

- Check the attachment of the secondary safety device at the Flying

frame (refer to section 3.4 on page 17).

- Check the attachment of the Flying frame to the first cabinet (T10 or

T-SUB Front and Splay/Rear links) and ensure all Locking pins are
properly locked.

- Check the attachment of all Front links on both sides of the cabinets

and ensure all Locking pins are properly locked.

- Check the splay angles.

- Check the attachment of the Splay/Rear links at the rear of the

cabinets and ensure all Locking pins are properly locked.

- In "Single pickpoint operation" check the desired total vertical aiming

of the entire array using a inclinometer.

5.1.2. Ground stacks

- Check the attachment of all Front links on both sides of the cabinets

and ensure all Locking pins are properly locked.

- Check the splay angles.

- Check the attachment of the Splay/Rear links at the rear of the

cabinets and ensure all Locking pins are properly locked.

5.1.3. Wiring

- Check the wiring.

If the amplifiers are already wired and powered on, use their System
check function or channel mute switches and a test signal to check the
correct functioning and routing of all channels and cabinets.