MX/DDC-100 Field Unit Installation and Maintenance FCD LMENIM2329-01 – 03/11

64

Contractor Tasks

Deliverable

From

To

Comments

Specifications

Engineer

Contractor

Complete P&IDs for site

Schedule

Engineer

Contractor

Time line complete w/milestones

Project

Responsibilities

Engineer

Contractor

Define which supplier is responsible for each portion of project

P&ID

Engineer

Contractor

Detailed layout and instructions for building site. Information should include

actuator tag names, required data points from actuator, field unit, and field wiring

Site Electrical
and electronics

Engineer

Contractor

Detail site electrical requirements, cable type, layout, and locations. Voltages

available for equipment

Loop Drawings

Engineer

Contractor

Detail cable routings from Host to each field device. This defines how the network

cable is to run throughout the facility

Schedule

Contractor

Limitorque

Provide material delivery dates for hardware. Schedule Flowserve Limitorque

Controls Service Technician for actuator commissioning (when requested

according to purchase order)

Hardware

Limitorque,
OEM

Contractor

Provide Motor-Operated Valves, RS-232/485 converters (if supplied), valves,

mounting adapters, etc.

Manuals

Limitorque

Contractor

Product Bulletins for Actuators:
• LMAIM4019 Direct-to-Host Programming Guide
• LMAIM1329 Accutronix Installation and Operation for MX-DDC Field Unit
• LMAIM4029 DDC-100 UEC Field Unit (Modbus) Installation and Operation

Manual

• LMAIM4030 DDC-100 UEC Field Unit Installation and Commissioning Manual
• LMAIM4022 DDC-100 UEC Field Unit Wiring and Startup Guidelines
• Modicon Modbus Protocol Reference Guide PI-MODBUS-300 Rev. G (available

from Modicon)

Operational

System

S.I.

Contractor

Develop and test programming for DCS system

Documents

S.I.

Contractor

Documentation of program operational characteristics, equipment used, and

Operation and Maintenance Manuals for equipment

Schedule

Contractor

S.I.

Provide delivery dates for commissioning control system. Include dates for testing,

documentation, and turnover to site personnel

Hardware

for system

development

Contractor

S.I.

Hardware may include: DDC-100 Field Units, RS-232/485 converters

Actuator

Contractor

S.I.

Availability of DDC-100 Field Unit for testing developed application software

Site Preparation Contractor

S.I.

Complete actuator or field unit installation. Provide actual (as installed)

Site Preparation Contractor

Limitorque

Install specified equipment, cables for power and network communication. Verify

all network and power cables are properly routed, terminated, and documented

prior to commissioning of DDC-100 Network. The contractor should provide

detail on network routing from Host system to each field unit. Verify all field units

are properly grounded

Field Unit

Startup

Limitorque

Contractor

According to purchase order requirements, when scheduled