6.1.4 Requirements for Cable Routing

☐ Cable entries are located in the connection cabinet.
☐ Empty tubes for the cable routing have been laid

under the foundation.

☐ The communication cables are separated from

the AC and DC cables.

☐ An appropriate number of cable entries

is provided:
– AC cables: 3
– DC cables: according to the number of

DC cables

– PE cables: 1
– Communication cables: 1

Figure 10: Cable entries for 9 DC inputs (example)

Laying the cables

This document does not specify at what time the cables are to be laid in the foundation.
The time for laying the cables must be decided individually for the particular plant.

Position

Description

A

Entry for AC cable

B

Entry for DC cable

C

Entry for PE cable

D

Entry for communication cable