7 switching on the inverter, Switching on the inverter – SMA SC 500HE-20 Installation User Manual

Page 64

Advertising
background image

12  Commissioning

SMA Solar Technology AG

64

SCxxxHE-20-IA-IEN111210

Installation Manual

4. Check the 3 indicator lamps on the 3 printed circuit

boards of the power units in the inverter cabinet.
☑ Indicator lights glow green.
✖ Are indicator lights not glowing green?

• Contact the SMA Serviceline.

12.7 Switching on the Inverter

Requirements:

☐ All electrical connections made on site are correctly executed and firmly in place.
☐ The entire electrical system including the PV plant has been tested by the plant installer in

accordance with IEC 60364-600 "Low-voltage electrical installations – Part 6: Verification".

☐ A test protocol of the tests performed in accordance with IEC 60364-600 is available.
☐ If a medium-voltage system is present, further tests have been performed.
☐ The ground resistance of the plant has been measured.
☐ All values measured are within the permissible range.
☐ The inverter doors are closed.

• Turn the key switch to Start.

☑ The DC switch switches on with an audible click.
☑ Under conditions of sufficient irradiation, the inverter starts feeding into the grid.

✖ Are the display or indicator lamps showing an fault?

• Follow the operating manual for troubleshooting.

%"/(&3

Danger to life through electric shock in the event of improper use or unauthorized
opening of the inverter.
High voltages are present in the inverter during operation.

• Do not operate the inverter while the door is open.
• Remove the keys from the door locks on the inverter station.
• Keep the keys in a safe place.