4 connecting the cables in the connection cabinet, 2 important measures for non-utilized options, Connecting the cables in the connection cabinet – SMA SC 500HE-20 Installation User Manual

Page 48: Important measures for non-utilized options

Advertising
background image

10  Cable Connection in the Connection Cabinet

SMA Solar Technology AG

48

SCxxxHE-20-IA-IEN111210

Installation Manual

10.4 Connecting the Cables in the Connection Cabinet

10.4.1 Connecting the cables to the customer terminal block

1. Strip cable jacket to approx. 60 mm.
2. Strip conductor insulation to 5 mm.

3. Attach the bootlace ferrule to the conductors and crimp gas-tight.
4. Connect the cable in accordance with the circuit diagram.

– Insert a screwdriver into the square hole next to the terminal and open the terminal lock by

pressing it.

– Connect the cables to the terminals using bootlace ferrules.
– Remove the screwdriver from the terminal.

10.4.2 Important Measures for Non-utilized Options

Non-utilized External Quick-Stop

Non-utilized Remote Shutdown

• If you are not using the remote shutdown option, set the parameter "ExtStrStpEna" to Off after

commissioning (see operating manual included in the delivery).

Non-utilized Transformer Protection

• If you are not using the transformer protection option, set the parameter "ExtTrfErrEna" to Off

after commissioning (see operating manual included in the delivery).

/05*$&

Damage to the Sunny Central caused by faulty installation of the external quick-stop.
If an external quick-stop is installed incorrectly, this may damage the Sunny Central and restrict the
function of the quick-stop.

• If no external quick-stop is installed, the terminals must be bridged according to the circuit

diagram.