F-58

TROUBLESHOOTING & REPAIR

F-58

TEST PROCEDURE

Perform the following checks with the
NA-5 connected to a Lincoln CV weld-
ing power source according to the prop-
er connection diagram. See the
Installation Section of this manual.

1. Connect the test voltmeter (see

Materials Needed) between the
"work" and the electrode cable con-
nection at the welding head. See
Figure F.7

2. Using the 5/16" nutdriver open the

control box PC board access door.

3. Place a jumper wire between leads

#2 and #4 located on CR3 relay.
See Figure F.8 This this should
energize the output terminals of the
Lincoln CV welding power source.
An open circuit voltage should be
present at the welding output termi-
nals. The test voltmeter reading
should match the ACTUAL volts
meter reading on the NA-5 within +/-
0.5VDC (typically +/- 0.2VDC). If it
does not, check the integrity and
placement of the voltage
sensing leads #21 and #67 and
associated wiring. Perform the
Meter Circuit Accuracy Test.

VOLTMETER ACCURACY TEST

(Continued)

NA-5

FIGURE F.7 TEST METER CONNECTION POINTS

CONNECT VOLTMETER

TO ELECTRODE

CONNECTION

POINT

ELECTRODE CABLES

Return to Section TOC

Return to Section TOC

Return to Section TOC

Return to Section TOC

Return to Master TOC

Return to Master TOC

Return to Master TOC

Return to Master TOC

Advertising
This manual is related to the following products: