6 installing the processor air duct, 1 configuring jumpers on the server board, Installing the processor air duct – Kontron NSW1U IP Network Server User Manual

Page 28: Configuring jumpers on the server board, Air duct, Figure 14

Advertising
background image

NSW1U Network Server—Server Installations and Upgrades

Kontron IP Network Server NSW1U

Product Guide, rev. 1.4

December 2009

28

3.2.6

Installing the Processor Air Duct

1. Place the processor air duct over the processor socket and three-fan assembly, using caution to

make sure you do not pinch any wires beneath the edges of the air duct.

2. Tighten the screws at the top of the air duct. (

Figure 14

, “A”)

The top of the installed air duct should be flush with the top surface of PCI adapter assembly.

3. Replace the chassis cover if you have completed all work inside of the chassis.

3.3

Internal Configuration and Installation Procedures

The procedures in this section assume that you have powered down the server and removed the

chassis cover as described in

Section 3.2, “General Installation Procedures” on page 25

.

3.3.1

Configuring Jumpers on the Server Board

The jumpers are located on the S5000PHB server board server board, which is in the rear left side of

the NSW1U Network Server chassis. To configure the jumpers on the server board, besides removing

the chassis cover, you also must remove the processor air duct (see

Section 3.2.5, “Removing the

Processor Air Duct” on page 27

) and the PCI riser card assembly (see

Section 4.4.1, “Removing the

PCI Riser Card Assembly” on page 52

). All other components installed on the server board can remain

in place.

Figure 14.

Removing the Air Duct

AF000880

A

A

B