TroubleshooTing and sysTem TesTs

powermax

45

Service Manual

5-7

4. Remove the Mylar barrier from the power board side of the power supply. Be certain to replace the barrier when

you are finished working on the power supply.

5. Inspect the inside of the power supply, especially on the side with the power board. Look for broken or loose

wiring connections, burn and char marks, damaged components, and so on. Repair or replace as necessary.

Initial resistance check

All resistance values must be taken with the power cord disconnected and all internal power supply wires attached.

Perform the steps in Internal inspection on page 5-6 before continuing in this section.

• If resistance values are not close (±25%) to the values given in this section, isolate the problem by removing wires

attached to the resistance check points or component until the problem is found.

• After the problem has been located and repaired, refer to the Sequence of operation flow diagram on page 5-4

to test the power supply for proper operation.

1. With the power disconnected and the torch removed from the power supply, set the ON/OFF switch (S1) to

ON (I).

2. Check the resistance across the input leads (the leads are identified with “AC” printed on the power board).

• 200–240 V CSA and 230 V CE: resistance across the input leads = 75 kΩ.
• 400 V CE and 480 V CSA: resistance across the input leads = 2.5 MΩ.

3. Check the resistance from the input leads to ground to verify that it reads as open. For all power supplies, the

resistance from input to ground should read as > 20 MΩ.
Note: With the power disconnected and the ON/OFF switch (S1) set to OFF (O), all circuits should read

as open.

The electrical values shown are ±25%.

4. Check the output resistance for the values shown in the following table.

Measure resistance from

200–240 V CSA and

230 V Ce power board

location

400 V Ce and 480 V

CSA power board

location

Approximate

values

Work lead to nozzle

J21 to J17

J21 to J16

100 kΩ

Work lead to electrode

J21 to J19

J21 to J18

20 kΩ

Electrode to nozzle

J19 to J17

J18 to J16

120 kΩ

Output to ground

> 20 MΩ

If no problems were found during the visual inspection or the initial resistance check, and the power supply still does not

operate correctly, see the Troubleshooting guide on page 5-11.

Note: The Troubleshooting guide provides most probable causes and solutions. Study the system wiring diagram

and understand the theory of operation before troubleshooting. Before purchasing any major replacement

component, verify the problem with Hypertherm Technical Service or the nearest Hypertherm repair facility.

Advertising
This manual is related to the following products: