Electrical assembly, Assembly – Grain Systems Bucket Elevtors, Conveyors, Series II Sweeps PNEG-751-G2 User Manual

Page 42

Advertising
background image

5. Assembly

42

PNEG-751-G2 12" Series II Sweep 131' and 135' Diameter

Electrical Assembly

NOTE:

See Chart below

for the correct size of conduit with the corresponding sweep size.

A. Place the 3/4" rigid conduits in order starting with the head section and working towards the tail or

extension section.

B. Connect the rigid conduit together using one 3/4" conduit coupling between each piece of conduit.

(See Figure 5Z.)

Figure 5Z

Sweep Section Conduit Sizes

Bin Diameter

10' Conduit Pieces

Other Pieces

131'

4

1 at 5'

135'

4

1 at 7'

WARNING

All electrical wiring and service work must be performed by a qualified
electrician and must meet all state and local electrical codes.