PNEG-751-G2 12" Series II Sweep 131' and 135' Diameter

6. Start-Up

Perform Pre-Start Checks

A. Make sure ALL shields are in place.

B. Inspect the drive unit for any problems or potential problems.

C. Be aware of any emergency shut down procedures. Two (2) people must always be in position to

monitor the operation of the equipment from outside the bin.

D. Before starting the auger for the first time, make sure that all parts are assembled correctly according

to the instructions in this manual.

WARNING

To ensure that the drive is not unexpectedly started, turn OFF and lock out the
power source before proceeding. Failure to observe these precautions could
result in bodily injury.

DANGER

Failure to perform any or all of these pre-start checks may cause damage to the
equipment and/or cause SERIOUS INJURY or DEATH to those in the work area.

Failure to perform any or all of these pre-start checks may also be a misuse of
the equipment. Any misuse of the equipment may void the warranty.

WARNING

ALWAYS keep ALL guards and shields in place, until all the power is
disconnected and locked out.

CAUTION

Be sure to remove the grain from the drive chain and sprockets. If this is not
done, damage can occur to the drive system.

WARNING

Make certain ONLY trained operators are in the work area before operating or
moving the machine. Two (2) people must always be in position to monitor the
operation of the equipment from outside the bin.