6 Commissioning, operation

76 WIKA Operating Instruction, Pascal 100 and Pascal 100/IS

GB

The main screen will be displayed as per below:

Figure 93

– Report running display


On the bottom menu, the report name (rpt1), the calibration point (1of 6) and the related reference
value (0.00000) will be shown. Press STORE to store the first calibration point: the switch to the
second point is done automatically (pnt 2 will be shown), and so on for all the predefined
calibration points. Pay attention to the bargraph in the DUT display: check if point is inside or
outside the limit specified during the DUT assignment.
Once the calibration cycle is defined, the generation of an electrical signal is done automatically.
For the pressure, instead, the operator has to reach the required pressure values using the manual
pump and the fine adjustment.
During the configuration process the operator can name the report: the same can be recalled when
the same procedure is required.
In any moment the operator can stop the calibration pressing ABORT.

To make the zero on the reference channel REF, press OFFSET before storing the first calibration
point: this function is displayed as OFS on the channel display, under the measurement value.
Press again OFFSET to come back to the original configuration: OFS will disappear.

Figure 94

– Report running display – next menu


Once the last calibration point is done, press STORE (or ABORT): the Report will end
automatically and the display will go back to its original configuration.