SECTION 3 - TURNTABLE

3120898

– JLG Lift –

3-7

e. Attach suitable overhead lifting equipment to the

base of the turntable weldment.

f. Use a suitable tool to scribe a line on the inner

race of the swing bearing and on the underside
of the turntable. This will aid in aligning the bear-
ing upon installation. Remove the bolts and
washers which attach the turntable to the bear-
ing inner race. Discard the bolts.

g. Use the lifting equipment to carefully lift the com-

plete turntable assembly from the bearing.
Ensure that no damage occurs to the turntable,
bearing or frame-mounted components.

h. Carefully place the turntable on a suitably sup-

ported trestle.

i.

Use a suitable tool to scribe a line on the outer
race of the swing bearing and the frame. This
line will aid in aligning the bearing upon installa-
tion. Remove the bolts and washers which
attach the outer race of the bearing to the frame.
Discard the bolts. Use suitable lifting equipment
to remove the bearing from the frame, then
move the bearing to a clean, suitably supported
work area.

2.

Installation.

a. Using suitable lifting equipment, carefully lower

the swing bearing into position on the frame.
Ensure the scribed line of the outer race of the
bearing aligns with the scribed line on the frame.
If a new swing bearing is used, ensure that the
filler plug fitting is at 90 degrees from the fore
and aft center line of the frame.

JLG INDUSTRIES RECOMMENDS THAT ALL REMOVED BEARING
BOLTS BE DISCARDED AND REPLACED WITH NEW BOLTS.
SINCE THE SWING BEARING IS THE ONLY STRUCTURAL LINK
BETWEEN THE FRAME AND TURNTABLE, IT IS IMPERATIVE
THAT SUCH REPLACEMENT HARDWARE MEETS JLG SPECIFICA-
TIONS. USE OF GENUINE JLG HARDWARE IS HIGHLY RECOM-
MENDED.

b. Apply a light coating of Loctite #271 to the new

bearing bolts, and loosely install the bolts and
washers through the frame and outer race of
bearing.

IF COMPRESSED AIR OR ELECTRICALLY OPERATED IMPACT
WRENCH IS USED FOR TIGHTENING THE BEARING ATTACH-
MENT BOLTS, THE TORQUE SETTING ACCURACY OF THE TOOL
SHOULD BE CHECKED PRIOR TO USE.

c. Refer to the Torque Sequence diagram as

shown in Figure 3-7., Swing Bearing Torque

Sequence. Spray a light coat of Safety Solvent
13 on the new bearing bolts. Then apply a light
coating of Loctite #271 to the new bearing bolts,
and install the bolts and washers through the
frame and outer race of the bearing. Tighten the
bolts to an initial torque of 240 FT. LBS. (326
Nm) w/Loctite.

d. Remove the lifting equipment from the bearing.

e. Using suitable lifting equipment, carefully posi-

tion the turntable assembly above the machine
frame.

f. Carefully lower the turntable onto the swing

bearing, ensuring that the scribed line of the
inner race of the bearing aligns with scribed line
on the turntable. If a new swing bearing is used,
ensure that the filler plug fitting is at 90 degrees
from the fore and aft center line of the turntable.

g. Spray a light coat of Safety Solvent 13 on the

new bearing bolts. Then apply a light coating of
Loctite #271 to the new bearing bolts, and
install the bolts and washers through the turnta-
ble and inner race of the bearing.

h. Following the Torque Sequence diagram shown

in Figure 3-7., Swing Bearing Torque Sequence,
tighten the bolts to a torque of 240 ft. lbs. (326
Nm) w/Loctite.

i.

Remove the lifting equipment.

j.

Install the rotary coupling retaining yoke brack-
ets, apply a light coating of Loctite #242 to the
attaching bolts and secure the yoke to the turn-
table with the mounting hardware.

k. Connect the hydraulic lines to the rotary cou-

pling as tagged prior to removal.

l.

At ground control station, use boom lift control
to lower boom to stowed position.

m. Using all applicable safety precautions, activate

the hydraulic system and check the swing sys-
tem for proper and safe operation.

Swing Bearing Torque Values.

1.

Outer Race - 240 ft. lbs. (326 Nm) w/Loctite, 220 ft.
lbs. (298 Nm) dry.

2.

Inner Race - 240 ft. lbs. (326 Nm) w/Loctite, 220 ft.
lbs. (298 Nm) dry.

3.

See Swing Bearing Torquing Sequence.

CHECK THE INNER AND OUTER SWING BEARING BOLTS FOR
MISSING OR LOOSENESS AFTER FIRST 50 HOURS OF OPERA-
TION, AND EVERY 600 HOURS THEREAFTER.