Figure 62: Installing the New PDB in the Chassis

3. Connect all of the new cables on the new PDB to their connectors on the SAS backplane, server

board, and front panel board, being careful to route them as low as possible so as not to interfere with
other components or air flow.
For connector locations and cable routing assistance, see Figure 24: Cable Routing” and Figure 7:
Baseboard Components and Connectors”

4. Replace the black plastic sheath over the cables that run along the right side of the server board.

5. Push the power supply module(s) back into place so they are mated with the PDB.

6. If this is the last task you are performing inside the server chassis, replace the chassis cover and

reconnect any external devices and the power cord(s).