4.2 Checks Prior to Main Power Application

YASKAWA ELECTRIC TOEP C710656 01C YASKAWA - RC5 Instruction Manual

35

4.2

Checks Prior to Main Power Application

Check the following before turning ON the power supply.

• Check that the power supply is of the correct voltage.

200 V class: 200 to 230 VAC, 50/60 Hz
400 V class: 380 to 460 VAC, 50/60 Hz

• Make sure that the power regenerative unit and the Drive are connected correctly.

• Make sure that the phase sequence of the main circuit terminals (R/L1, S/L2, T/L3) and the power supply voltage detection terminals (r1/ 11, 1/

21, t1/ 31) are correct.

• Make sure that the power regenerative unit and the control device are wired correctly.

• Set the run command of the power regenerative unit and the drive to OFF.