To isolate the t1 or t2 data path, Sun proprietary/confidential: internal use only – Sun Microsystems 6900 User Manual

Page 114

Advertising
background image

94

Sun StorEdge 3900 and 6900 Series 2.0 Troubleshooting Guide • March 2003

Sun Proprietary/Confidential: Internal Use Only

When you insert a loopback connector in to the T port, no green light appears to
indicate a proper insertion. However, the test will run and be valid.

If only one of the links has failed and the I/O is traveling over the remaining link,
I/O is automatically routed over the repaired link by the switch after the failed
link is replaced and recabled. No manual intervention is required.

If both links have failed and a LUN failover has occurred, you must manually run
a

failbackt3path

command to return the paths to their optimal state, after you

repair and recable the links.

To Isolate the T1 or T2 Data Path

1. Run

linktest

from the Storage Automated Diagnostic Environment for a guided

isolation procedure.

2. After replacing the failed FRU, run

failbackt3path

, if needed.

Advertising