Stratum 3 clock

555-233-116

170

Issue 4 October 2002

7. Bridge the jumper wires to cross-connect from the TN780 in A and B

carriers to the Stratum 3 clock.

8. Dress the cables down sides of the cabinet and run through the cable

Slack Manager, if provided.

9. Administer the switch for the clock.