11 setting up original arrangement – Metrohm 719 S Titrino User Manual

Page 119

Advertising
background image

4.2.

Diagnosis

719 S Titrino

115

Spindle remains at maximum position. The transit time of the spindle is

20 s.

• Measure spindle lifting (can be performed only if the 3.496.0070 Dummy Exchange

Unit is inserted or the locking switch (in right hole) is carefully operated with a

screwdriver after removal of the Exchange Unit).

From the start point, the spindle travels 80 mm. Instead of the spindle height, the expelled

volume can be measured (corresponds to max. vol. of Exchange Unit used).

• Press <FILL> (on instrument) and simultaneously measure the time until the Titrino

is again in the 'ready' position.

Times for filling:

per stop cock cycle 1 s

for filling

20 s (Tolerance: 10 %)

The following generally holds: Spindle and stopcock must move at a constant speed

(noise!). In the filling setting, the stopcock coupling must position the lever of the Exchange

Unit correctly at the left stop (with virtually no play and without sticking).

• Set potentiometer 'dV/dt' to left stop.

• Press <DOS> (on instrument) at same time and use a stopwatch to measure the

time for 1/10 of the cylinder volume to be expelled. The time should be ca. 90 ... 110

s.

• Set potentiometer 'dV/dt' to right stop.

• Press <FILL>.

11 Setting up original arrangement

Reconnect all peripherals disconnected at the start of the diagnostic routine and perform

a short function test with these.

Advertising