Machine Installation

3.1

Installation

3.1.1

Receiving Inspection

Upon receipt of the equipment, visually inspect for shipping damage and note any damage with
the carrier before signing the shipping receipt, or advise the carrier of the damage as soon as it is
noted.

If damage is discovered, a written claim must be filed with the carrier as soon as possible.

Note: Warranty is VOID unless the equipment is installed according to instructions. The installa-
tion must comply with the minimum requirements listed in this manual. All national, state and
local codes must be followed including but not limited to gas, electrical, plumbing and HVAC.
Due to various requirements, statutory codes should be well understood before installation com-
mences.

The ironer is delivered in ready-to-connect modules. The supply and return lines for all utilities
such as heat, compressed air, power, exhaust, etc. must be installed on site. Each module is covered
with a protective plastic wrapping. The cover panels are normally mounted to the ironer module.

3.1.2

Product Description

1. Design And Construction

The heavy-duty ironers are manufactured in modules. The modules can be combined into
ironers of one to four units with diameters of 800 mm (32 in.) or 1200 mm (47 in.) in widths
of 3000 mm (118 in.) or 3300 mm (130 in.). Other widths are available - consult the factory.

2. Modular System

The modular design allows an increase of modules (up to four) to fit the individual require-