Positioning and leveling – B&C Technologies IM Series Industrial Ironer User Manual

Page 28

Advertising
background image

Figure 3.2: Module Bolting

NOTE: The fork lift used must have the required capacity and be fitted with appropriate forks.

The modules can be picked up at the I-Beams at the front side. If using a fork lift, then one side
of the ironer is to be lifted and skid rollers are to be used for the opposite side. Lift the ironer and
move it slowly to its destination. The passage of the load should be clear of any obstruction on the
floor or overhead, such as power lines, ceiling beams and others.

c) Using a Crane

The transport brackets must be in position before attempting to move the modules with a crane.

NOTE: The crane used must have the required capacity and be fitted with appropriate slings
and a spreader frame.

The modules are to be moved in a horizontal position only. After the modules are in position,
remove the transport brackets before mounting the modules together.

3.5.5

Positioning and Leveling

The ironer should be positioned as per installation drawing. The minimum required side distance
to walls or other obstructions or equipment is 36 inches (915mm).

NOTE: The module number can be found at the top of the side frame beside the connecting
bracket (see figure 3.2).

18