Module placement – B&C Technologies IM Series Industrial Ironer User Manual

Page 29

Advertising
background image

Figure 3.3: Flange Cover Detail

3.5.6

Center/Front Module Placement

With the module still on its skid, move it near its final position, about 12 inches (300mm) from the
already placed module and remove the skid bolts.

Place drip pans under the flange shipping covers (painted red).

Note: Thermal Fluid may cause a skin reaction in sensitive individuals. Wear protective clothing.
Refer to the Material Safety Data Sheet in the Appendix of this manual.

Remove the flange shipping covers from the thermal fluid supply and return connections. A small
amount of fluid will drain out. Wait until the flow completely stops before continuing.

Note: Follow local codes for handling the disposal of the thermal fluid collected in the drip
pans. Do not attempt to reuse this fluid!

Carefully clean the flanges and any additional spilled thermal fluid. Carefully dispose of the ther-
mal fluid and cleaning materials according to local codes.

Using a crane or forklift, lift the module straight up and carefully remove the skid. Do not drop or
twist the module.

Move the module until it is directly above its final location. The endframes of the modules will be
in contact with one another. Carefully lower the section to its final position. Ensure that the gap
piece is aligned with the chest of the previously placed module.

• The gap piece should be slightly above the mating chest and extend just beyond the surface

19

Advertising