Testing an ISDN BRI trunk

Procedure 41

Perform procedure to test an ISDN BRI trunk DSL

Step

Action

1

Set up the ISDN trunk test configuration to be used, as described
previously in the chapter "Set up ISDN BRI test terminals and
trunks".

2

Place a call across the ISDN BRI trunk.

3

Complete the call and hang up.

—End—

Removing the test setup

After acceptance testing has been completed and the results show the
system is operating correctly, remove the ISDN BRI terminal setup and
configure ISDN BRI equipment according to the customer configuration.
If the actual customer configuration was used to perform these tests, no
changes are needed.

Nortel Communication Server 1000

ISDN Basic Rate Interface Installation and Commissioning

NN43001-318

01.02

Standard

Release 5.0

20 June 2007

Copyright © 2003-2007, Nortel Networks

.

Advertising