Preparing for installation

Contents

This section contains information on the following topics:

"Preparing the site" (page 13)

"Unpacking and inspecting" (page 14)

"Taking inventory" (page 14)

Preparing the site

When installing a system, address the following factors.

environmental

structural

electrical

For more information refer to Communication Server 1000M and Meridian 1
Large System Planning and Engineering (NN43021-220)
.

After the site has been planned, the following items must be completed
prior to ISDN BRI installation.

Wire the building between ISDN BRI terminal locations and the
distribution frame. Refer to the "Engineering guidelines" section of ISDN
Basic Rate Interface Feature Fundamentals (NN43001-580)
for wiring
specifications and guidelines. For the location of the terminals and the
distribution frame, use the Building Cable Plan developed according
to instructions in the "Planning the site" section in Communication
Server 1000M and Meridian 1 Large System Planning and Engineering
(NN43021-220)
.

Install any Intelligent Peripheral Equipment (IPE) or Network Modules
needed to house ISDN BRI cards as determined in "Engineering
guidelines" of ISDN Basic Rate Interface Feature Fundamentals
(NN43001-580)
. Refer to Communication Server 1000M and Meridian

Nortel Communication Server 1000

ISDN Basic Rate Interface Installation and Commissioning

NN43001-318

01.02

Standard

Release 5.0

20 June 2007

Copyright © 2003-2007, Nortel Networks

.

Advertising