Operation, 1 preparation for starting operation, Operation -1 – Yokogawa EJX530B User Manual

Page 29: Preparation for starting operation -1

Advertising
background image

<7. Operation>

7-1

IM 01C27F01-01EN

7. Operation

7.1 Preparation for Starting

Operation

This section describes the operation procedure for

the EJX530B as shown in figure 7.1.

NOTE

It is required to set security and network

information to enable the transmitter to be

connected to the Field Wireless Network. For

more details, refer to section 7.4 “Connecting to

the Field Wireless Network”.

NOTE

Check that the process pressure tap valves,

drain valves, and stop valves are closed.

(a) Follow the procedures below to introduce

process pressure into the impulse piping and

transmitter.

1) Open the tap valve (main valve) to fill the

impulse piping with process fluid.

2) Gradually open the stop valve to introduce

process fluid into the transmitter pressure-

detector section.

3) Confirm that there is no pressure leak in

the impulse piping, transmitter, or other

components.

(b) Insert batteries into the battery case, and install

to the transmitter. To insert batteries into the

battery case, be careful to polarity of batteries

and battery case. For details of Installation of

battery, refer to section 9.4.6 and 9.4.7.

Battery case is installed in the transmitter when

shipped from the factory, however, batteries are

sold separately and not included.

(c) Using the device configuration tool, confirm

that the transmitter is operating properly. Check

parameter values or change the setpoints as

necessary.

Integral Indicator’s indication can be used

to confirm that the transmitter is operating

properly. For details on how to confirm refer to

subsection 8.4 “Self-Diagnostics”.

ISA100 devices display self-diagnostic

information in an easy-to-understand manner

using four categories (Check function,

Maintenance required, Failure, and Off

specification) according to NAMUR NE107*

* NAMUR NE107 “Self-Monitoring and Diagnosis of Field

Devices”

F0701.ai

Union or flange

Vent plug (Fill plug)

Tap valve

Stop valve

Tee

Drain valve

Drain plug

Union or flange

Figure 7.1

Liquid Pressure Measurement

(Gauge Pressure Transmitters)

■ Confirm that transmitter is operating

properly by Integral Indicator

If the transmitter is faulty, an error code is displayed.

F0702.ai

Self-diagnostic error on the integral

indicator (Faulty transmitter)

Figure 7.2

Integral Indicator with Error Code

NOTE

If any of the above errors are indicated on the

display of the integral indicator or the device

configuration tool, refer to subsection 9.5.3 for

the corrective action.

Advertising