Installation clearance, Prevent damage to the router, Ground the router – Rockwell Automation 1783-SR Stratix 5900 Services Router User Manual User Manual
Page 18: Ground the router on

18
Rockwell Automation Publication 1783-UM005A-EN-P - September 2013
Chapter 2
Install Stratix 5900 Services Router
Installation Clearance
The recommended clearance when horizontally mounted is 1.5 inches on both
sides for floor-mount bracket clearance and 2 inches on top.
I/O side clearance is needed as it is required to access the cable connections.
Clearance is not required on the backside (opposite side from I/O face) unless
DIN rail mounting is required. Clearance is required to attach and mount the
DIN rail bracket. The same clearances apply when mounted vertically.
Prevent Damage to the
Router
To prevent damage to your router, follow these guidelines when connecting
devices to your router.
Ground the Router
Follow this illustration to ground the router.
IMPORTANT
Top clearance is not required but stacking heat dissipating objects on top of
the services router is not allowed.
ATTENTION: Turn off power to the router and any devices until all connections
are completed.
Do not turn on the devices until after you have completed all connections to the
router.
2434-M