Removing and Installing Roll-Out Chassis Units

3-5

Installation Procedure

Follow the procedures below to install a roll-out chassis unit into its MCC.

1. Reposition the chassis unit into the MCC according to your company’s

handling instructions.

2. Connect all wires that you disconnected between the chassis unit and

devices in the MCC.

3.

!

ATTENTION: To avoid the hazard of electrical shock, verify
that all voltages on the system bus network have been discharged
before attempting to service the system.

ATTENTION: 2362 chassis units have the following
approximate weights: D-frame, 260 lbs (119 kg);
E-frame, 440 lbs (200 kg); F-frame 675 lbs (306 kg); and
G-frame 1000 lbs (455 kg). 2364F chassis units have the
following approximate weights: K-code, 260 lbs (119 kg);
L-code, 440 lb (200 kg); M-code, 1000 lbs
(455 kg); and N-code, 1000 lbs (455 kg). Failure to take
precautions when moving a chassis unit may result in personal
injury and/or damage to equipment.

If the module size is:

Do this:

D, F, or G-frame 2362 units or
K, M, or N-code 2364F units

Replace the two bolts to fasten the chassis unit
to the upper brackets. See Figure 3.2.

E-frame 2362 units or
L-code 2364F units

Replace the four screws to fasten the chassis
unit to the upper brackets. See Figure 3.2.