14  Connecting External Sources

SMA America, LLC

118

SI4548-6048-US-BE-en-20

Operating Manual

Sunny Island Connected in Parallel to a 120 V Generator

Sunny Island in the Split-Phase System connected to a 240 V Generator

Generally, the internal transfer relays of the slaves close only if the internal relay of the master is
closed.
Plants with master and slave unit on one battery (cluster operation) will keep on working if one slave
fails. If the master fails, the whole cluster stops its operation.