If the generator is started manually in this operating mode, the Sunny Island detects the running
generator and connects it once the warm-up time has expired. If you stop the generator externally,
this is detected, the generator disconnected and the stand-alone grid is still supplied.

14.1.3 Generator Operation

The Sunny Island allows automatic operation (depending on the state of charge or load) (see
Section 14.1.5 "Automatic Generator Operation", page 122)
. In addition, manual operation is also
possible.

14.1.4 Manual Generator Operation

The manual operating modes for the generator management are tripped using the parameter
"540.01 GnManStr". Here, a distinction is made between the following operating modes:

Generator request
If the generator is running after being externally started and a generator request occurs, the
GnReq signal is disabled until the generator is externally stopped again and the stop time has
expired.

Auto:

In this operating mode, the generator is automatically started due to the settings.
This includes the start via the state of charge or the load power or by the request for
a manual equalization charge.
("520.01 ChrgSelMan" = Start).

Stop:

The generator is manually stopped. The current generator request is canceled –
immediate disconnection from generator and change to lock state. Once the lockout
time has ended, the generator switches into automatic operation.

Start:

Manual generator start – the generator runs "continuously" until stopped. The
generator can only be manually stopped.