16.2 Commissioning the Multicluster System

1. Perform steps 1 to 3 of the QCG start (see Section 8.2 "Starting the Quick Configuration Guide

(QCG)", page 68).

2. The following parameters must be set when "New Battery" is selected:

– Device type (master, slave 1, slave 2, slave 3)
– System configuration (3Phase, 1Phase 1, 1Phase 2, 1Phase 3, 2Phase 2, 2Phase 4,

MC-Box), for multicluster operation choose "MC-Box". Default setting: "1Phase 1"

– Multicluster configuration (MainCluster, ExtensionClst1, ExtensionClst2, ExtensionClst3),

default setting: "MainCluster"

– Device type of the Multicluster Box (MC-Box-12), default setting: "MC-Box-12"

3. For further settings, follow the QCG instructions (see Section 8.2 "Starting the Quick

Configuration Guide (QCG)", page 68).

Possible load shedding during initial start-up of a multicluster system
Unwanted load shedding can occur during the initial start-up of a multicluster system. The
possible causes of this can be a too-low state of charge of the battery or a still too inaccurate
charge level calculation in the Sunny Island.

• Disconnect all loads before the initial start-up of a multicluster system.
• After initial start-up, observe the SOC on the master of the main cluster via the parameter

"120.01 BatSoc". As soon as the SOC has risen above 50%, connect the loads.