Hfv test procedure for serial rectifiers – GE Industrial Solutions Galaxy Verification User Manual

Page 23

Advertising
background image

Galaxy Power System Verification Procedures

Issue 3 January 2008

Galaxy SC Controller Performance Verification Procedures 2 - 11

High Float Voltage Alarm/High Voltage Shutdown Alarm
Tests, continued)

HFV Test

Procedure for

Serial Rectifiers

Raising the plant voltage on a working system is left to the discretion of
the user. This test could disrupt power to working equipment. If the test
is performed, verify that the plant is in FLOAT mode and that rectifier
voltage has been set to the normal level after completing the test.

Tests must be done with batteries connected, or else when the rectifiers
shut down, the controller will also shut down.

Step

Action

1

From the front panel, follow the path <MENU>

→ CONFIG

→ THRESH → HFV (FLOAT). Use the <Adjust> keys to

change the value of the HFV threshold to a level below the
plant voltage noted above. Press <ENTER> to save the
change.

2

Observe that the controller initiates a Power Minor alarm
(PMN) and illuminates the RECT and MIN LEDs.

3

Follow the path <MENU>

→ CONFIG → THRESH →

HFV (FLOAT) and restore the threshold to it's original
setting. Press <ENTER> to save the change.