Discharge menu, Battery discharge test, continued – GE Industrial Solutions Galaxy Verification User Manual

Page 64

Advertising
background image

Galaxy Power System Verification Procedures

3 - 20 Galaxy Millennium Controller Performance Verification Procedures

Issue 3 January 2008

Battery Discharge Test, continued

Overview,

continued

The intelligent controller provides an enhanced battery discharge test
that makes even greater accuracy possible. Enabling the
“ENHANCED” software switch utilizes the Universal Reserve Time
Prediction algorithm, which takes into account the particular discharge
characteristics of the battery subsystem. The URPT feature requires that
battery temperature be monitored and several related battery parameters
be configured. Ensure that the correct battery model is chosen for the
plant.

Note: The Battery Discharge Test feature is available with controller
software Version 6.1 for the Millennium controller.

Discharge Menu

This menu allows you to configure the various parameters for the
Battery Discharge Test and Reserve Time Predictor features of the
controller:

MENU

BATTERY MANAGEMENT BAT DISCH

BATTERY DISCHARGE TEST

BAT TEST

: EN

ENHANCED

: EN

BAT TYPE

: EN

CELL STRING : 12

NUM STRING: 24

END V/CELL : 1.75

BAT CLASS : FLOODED

BAT TEST: Enable Battery Discharge Test by using the <+> and <->
keys to toggle between enable or disable. Press <ENTER> to save.

ENHANCED: Use the <+> and <-> keys to enable enhanced feature, if
intelligent controller is present.

BAT TYPE: Use the <+> and <-> keys to select the battery installed on
site. (The Menu contains a list of 10 batteries.) Press <ENTER> to save.
Note: This feature is only available with the intelligent option.

CELL STRING: Use the <+> and <-> keys to select the number of
cells per string. (Select 12 for a 24V plant, or 24 for a 48V plant.) Press
<ENTER> to save.