Local alarm test, Alarm test, continued – GE Industrial Solutions Galaxy Verification User Manual
Page 47
Galaxy Power System Verification Procedures
Issue 3 January 2008
Galaxy Millennium Controller Performance Verification Procedures 3 - 3
Alarm Test, continued
Local Alarm Test
Refer to Figure 3-1 for the Millennium switch positions referred to in
this test.
Prior to performing an Alarm Test, hardware switch SW202-5 on the
BSH board must be enabled, in addition to the software switch located
at menu path:
Basic: <MENU>
→ CONFIG → ALARM → TEST ALM
Intelligent: <MENU>
→ CONFIG → ALARM → TEST ALM
If HVSD is desired during the test, BSH SW202-4 must also be enabled,
along with the appropriate software switch found on the front panel
under the path: MAIN
→ CONFIG → ALARM → TEST HV, and each
plant rectifier must have a load of at least 10% of its capacity.
To perform the Alarm Test from the front panel, follow the menu path:
Basic: <MENU>
→ MAINT OPER → ALARM TEST
Intelligent: <MENU>
→ MAINT OPER → ALARM TEST
As an alternative to the front panel configuration of the Alarm Test
software switch, it may be also configured within EasyView under the
path: CONFIGURE
→ DC PLANT → HARDWARE & SOFTWARE
CONFIGURED.
Pressing the <ENTER> key while the cursor is on the ALARM TEST
field will provide the message “ALARM TEST STARTED.” Use the
<ESC> key to return to the MAINTENANCE OPERATION screen and
follow the relay operation in the ALARM TEST STAT: field. Pressing
<ENTER> while the cursor is on the ALARM TEST field will restart
the test.
Note: Front panel LEDs do not activate during the Alarm Test. the
alarms can be monitored by checking on the BSL alarm board.