Galaxy Power System Verification Procedures

Issue 3 January 2008

Galaxy Millennium Controller Performance Verification Procedures 3 - 5

Alarm Test, continued

Remote Alarm Test

Using EasyView to perform the Alarm Test, hardware switches
SW202-5 on the BSH board and SW204-2 on the BSJ board (Figure
3-1) must first be enabled, in addition to the software switches located
at menu path.

EasyView: CONFIGURE

→ DC PLANT → HARDWARE AND

SOFTWARE CONFIGURED

Both the Alarm Test and Remote Alarm Test fields must be enabled.

To start the Alarm Test in EasyView, follow the menu path:

EASYVIEW: CONTROL

→ ALARM TEST

A dialog box will appear with the status of the alarm relays being tested.
See above for the order in which the alarm relays will operate.

The selection of relays to be operated, as well as the duration of relay
operation, may be selected in EasyView by following the menu path:

EASYVIEW: CONFIGURE

→ ALARM TEST