Galaxy Power System Verification Procedures

4 - 24 Replacement Procedures

Issue 3 January 2008

Testing

Testing Additional

Alarms After

Replacing

Rectifiers

Alarm operation may be verified while the system operates at float
voltage.

Step

Action

1

Turn OFF the ac circuit breaker of replaced rectifier. Verify
that the AC and MIN alarm LEDs illuminate, the rectifier
displays ACF, and the controller alarms screen indicates
RECTIFIER FAIL : G01 (SCF and Millennium controllers).

2

Turn ON the ac circuit breaker of the replaced rectifier.
Verify that the rectifier starts and the alarms retire.

Testing Rectifiers

and Load Share in

Bay Expansions

Step

Action

1

Turn all rectifiers to STBY.

2

Connect a resistive load box (proper voltage) to the system’s
positive and negative bus bars.

3

Verify that the system load is less than 50 amperes.

4

Increase the system load to 50 amperes.

5

Turn ON all the rectifiers; after approximately 60 seconds,
verify that the load is divided equally among all the
rectifiers (within 2 amperes).

6

Reduce the system load. Verify that the rectifiers continue to
share the load.

7

Remove system load.