Meter calibration from the front panel, Voltage calibration – GE Industrial Solutions Galaxy Verification User Manual

Page 37

Advertising
background image

Galaxy Power System Verification Procedures

Issue 3 January 2008

Galaxy SC Controller Performance Verification Procedures 2 - 25

Meter Calibration from the Front Panel

Voltage Calibration

Step

Action

1

Using a calibrated DVM, measure the plant voltage from the
front panel voltage test jacks.

2

From the front panel press <MENU>

→ CONFIG → PLANT.

Using the Arrow keys, reset the plant voltage reading by
selecting RST PLV. Press <ENTER> to reset. This will
remove any pre-existing user calibrated values if they exist.

3

Press the <MENU> key, wait five seconds, and go back to the
CONFIG

→ DC PLT screen. Move to ADJ PLV on the menu

and use the <ADJUST> keys to calibrate the plant voltage to
match the reading of the DVM. Press <ENTER> to use the
new calibrated plant voltage.

4

Press the <ESCAPE> key until the default screen is displayed.
Verify that the plant voltage reading reflects the same reading
as shown on the DVM. Note that in a serial plant, the actual
plant voltage reflected by the DVM will change, not the
reading reflected on the display.