Galaxy Power System Verification Procedures

3 - 10 Galaxy Millennium Controller Performance Verification Procedures

Issue 3 January 2008

High Voltage Shutdown Test, continued

Battery Plant

HVSD Test,

continued

Step

Action

7

Observe the following:

When the voltage increases to the HV (FLOAT) level the
rectifier shuts down.

The Green ON LED on the rectifier blinks, the ALM
LED on the rectifier is not lit.

After 5-6 seconds the rectifier initiates its own restart
signal again, raising the plant voltage.

The rectifier will shutdown and restart three additional
times.

Upon the fourth shutdown, the rectifier’s ALM LED
lights and the rectifier’s display indicates “HO.”

The controller receives the RFA signal from the rectifier
and initiates a restart signal 5-6 seconds later.

The rectifier restarts again, raising plant voltage.

The rectifier shuts down and restarts four additional
times.

During these shutdowns the Green ON LED on the
rectifier blinks and the ALM LED on the rectifier is not
lit.

Upon the fourth shutdown, the rectifier’s ALM LED
lights and the rectifier’s display indicates “HO.”

An external RFA office alarm is generated

Continued on next page.