Side Access

A side bus access cover is located on each side of the controller.

1. Remove the hardware from the appropriate side bus access cover (see

Figure 7

).

2. Remove the side bus access cover.

3. Once the side bus access cover is removed, you will see the three power bus

bars and the ground bus (see

Figure 9

).

Figure 9 - Side Bus Access Cover Removed

Front Access– Access to Power Bus

1. Complete the Power Lock-out Procedure (refer to

Power Lock-out

Procedure on page 47 of Chapter 5

) for both medium voltage power cells

and the power bus.

2. Open the doors and remove the hinge pins.

ATTENTION: To avoid shock hazards, lock out incoming power (refer to

Power

Lock-out Procedure on page 47 of Chapter 5

) before working on the equipment.

Verify with a hot stick or appropriate voltage measuring device that all circuits
are voltage free. Failure to do so may result in severe burns, injury or death.