Rockwell Automation Publication 1500-UM055G-EN-P - May 2013

19

Installation – Standard Enclosure

Chapter 2

Top Exiting Load Cables

5. Load cables for the bottom power cell should be routed first. Pull the

cables into the cabinet through the appropriate opening (see

Figure 18

).

Run the cables behind the current transformer mounting plate and into
the bottom power cell.

Figure 18 - Load Cable Conduit Openings (Top Exit Shown)

6. For the top power cell, pull the cables into the cabinet through the

appropriate opening (see

Figure 18

).

7. Connect the cables to the current transformers and tighten the

connections to 65 N•m (48 lb•ft).

8. Connect cable shields to the ground lug.

9. Reinstall the cable duct boot and reassemble the cabinet.

Ground Lug

Load Cable Conduit

opening for cables from

bottom power cell

Load cable Conduit

Opening for cables

from top power cell

Top of Cabinet

ATTENTION: Ensure all barriers are replaced before re-energizing the
equipment. Failure to do so may result in electrical faults and cause
damage to equipment or serious injury to personnel.