Load cable connections – Rockwell Automation 1512B MV Controllers, 200/400A Two-High Cabinet, Standard and Arc-Resistant Enclosure User Manual

Page 40

Advertising
background image

32

Rockwell Automation Publication 1500-UM055G-EN-P - May 2013

Chapter 3

Installation – Arc-Resistant Enclosure (ArcShield)

Load Cable Connections

1. Complete the Power Lock-out procedure (refer to

Power Lock-out

Procedure on page 47 of Chapter 5

).

2. Follow steps 2 to 6 from

Front Access – Access to Power Bus on page 28

for the procedure to swing out the low voltage panel.

3. Remove the cable duct boot at the top of the cabinet for top exiting load

cables, or remove the one at the bottom of the cabinet for bottom exiting
load cables (see

Figure 35

).

Figure 35 - Access to Load Cable Conduit Openings (Bottom Exit Cable)

ATTENTION: To avoid shock hazards, lock out incoming power (refer to

Power

Lock-out Procedure on page 47 of Chapter 5

) before working on the equipment.

Verify with a hot stick or appropriate voltage measuring device that all circuits
are voltage free. Failure to do so may result in severe burns, injury or death.

IMPORTANT

The current transformers may be positioned for top or bottom cable exit.
Follow the appropriate procedure described for your starter configuration.

IMPORTANT

For ArcShield units, cable size should not exceed 1-500 MCM or 2-350 MCM
per phase.

Note: Refer to Dimensional Drawings provided with order documentation for
additional details related to cabinet floor plans.

Connect Load Cables to

Current Transformers

Removable Cable Duct Boot

to load cable conduit

opening for cables exiting

from bottom power cell

Advertising